Deterministic models for project scheduling suffer from the fact that they assume complete information and neglect random influences, that occur during project execution. A typical consequence is the underestimation of the project duration as frequently observed in practice. This phenomenon occurs even in the absence of resource constraints and has been the subject of extensive research in the scientific community. This paper presents a method for obtaining relevant information about the project makespan for scheduling models, with dependent random processing time available in the form of scenarios.

Evaluating project completion time in Project Networks with Discrete Random Activity Durations

BRUNI, Maria Elena;GUERRIERO, Francesca;
2009-01-01

Abstract

Deterministic models for project scheduling suffer from the fact that they assume complete information and neglect random influences, that occur during project execution. A typical consequence is the underestimation of the project duration as frequently observed in practice. This phenomenon occurs even in the absence of resource constraints and has been the subject of extensive research in the scientific community. This paper presents a method for obtaining relevant information about the project makespan for scheduling models, with dependent random processing time available in the form of scenarios.
File in questo prodotto:
Non ci sono file associati a questo prodotto.

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/20.500.11770/130507
 Attenzione

Attenzione! I dati visualizzati non sono stati sottoposti a validazione da parte dell'ateneo

Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus 15
  • ???jsp.display-item.citation.isi??? 10
social impact