Purpose -This paper addresses the problem of scheduling under uncertainty in construction projects. The existing methods for determining a project schedule are based on assumption of complete knowledge of project parameters. But in reality there is uncertainty in construction projects, deriving from a multitude of context-dependent sources and often provided as outcome of a risk analysis process. Thus classical deterministic analysis might provide a schedule which is not sufficiently protected against possible disruptions. Design/methodology/approach- A quantitative methodology is developed for planning construction projects under uncertainty aimed at determining a reliable resource feasible project schedule by taking into account the available probabilistic information to produce solutions that are less sensitive to perturbations that occur on line. The methodology relies on a computer supported system that allows to identify, analyze and quantify the schedule reliability and the impact of possible disruptions on the duration of the project. Findings The proposed methodology can exploit more information about the uncertain parameters than the commonly used deterministic method, and it provides an improved understanding of the schedule reliability in presence of uncertainty. The schedule generated with a classical deterministic method sets a completely unrealistic planned project delivery date of about 1250 days, with a probability around 50% to be exceeded. This behavior can be very unsatisfactory for construction projects for which high penalties are usually associated to heavy due date violations. Originality/value - This paper presents an approach for robust scheduling of construction project problem under uncertainty. We provide a tool able to support managers in developing a workable and realistic project schedule to be used as a guideline for project control and monitoring.
A methodology for dealing with uncertainty in construction projects
BRUNI, Maria Elena;Beraldi P;GUERRIERO, Francesca;
2011-01-01
Abstract
Purpose -This paper addresses the problem of scheduling under uncertainty in construction projects. The existing methods for determining a project schedule are based on assumption of complete knowledge of project parameters. But in reality there is uncertainty in construction projects, deriving from a multitude of context-dependent sources and often provided as outcome of a risk analysis process. Thus classical deterministic analysis might provide a schedule which is not sufficiently protected against possible disruptions. Design/methodology/approach- A quantitative methodology is developed for planning construction projects under uncertainty aimed at determining a reliable resource feasible project schedule by taking into account the available probabilistic information to produce solutions that are less sensitive to perturbations that occur on line. The methodology relies on a computer supported system that allows to identify, analyze and quantify the schedule reliability and the impact of possible disruptions on the duration of the project. Findings The proposed methodology can exploit more information about the uncertain parameters than the commonly used deterministic method, and it provides an improved understanding of the schedule reliability in presence of uncertainty. The schedule generated with a classical deterministic method sets a completely unrealistic planned project delivery date of about 1250 days, with a probability around 50% to be exceeded. This behavior can be very unsatisfactory for construction projects for which high penalties are usually associated to heavy due date violations. Originality/value - This paper presents an approach for robust scheduling of construction project problem under uncertainty. We provide a tool able to support managers in developing a workable and realistic project schedule to be used as a guideline for project control and monitoring.I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.